On April 21, 2025, the Analytical credit Rating Agency downgraded the credit rating of PJSC TGC-14 to BBB(RU), changing the outlook to "negative". This is stated in the agency's message.

The downgrade in the credit rating of TGC-14 is due to forecasts for an increase in the debt burden and debt servicing costs, an increase in the number of transactions with related parties (JSC Far Eastern Management Company and JSC Special Automobile Industry), as well as an increase in capital investment costs as part of the company's entry into the investment development cycle.

The company has started, among other things, the implementation of projects within the framework of the NGO (competitive capacity selection of new generating facilities) for the construction of 2 power units at Ulan-Ude CHPP-2, which are characterized by high capital intensity and penalties for non-compliance with the parameters of their implementation.

Currently, TGC-14 is carrying out extensive work on the implementation of measures aimed at using cost optimization tools to finance these projects.

Uncertainty related to the estimated cost of projects, the growth of which could potentially lead to the need to raise additional debt, as well as the timing, formats and results of the implementation of the above measures, including project financing parameters, led to a change in the forecast to "Negative", analysts emphasize.

At the same time, TGC-14 maintains a strong position in heat supply in the serviced territories (the Republic of Buryatia and the Trans-Baikal Territory), as well as an adequate business profile and corporate governance that meet the standards of the industry in which the company operates.

Geographical diversification reflects the level of socio-economic development of the regions where TGC-14 operates. The profitability score is above average.

The company's credit rating is constrained, among other things, by the size of the business, systemic regulatory risks, as well as forecasted debt burden and debt service levels, free cash flow and capital expenditures associated with a significant increase in the company's capital investment program.

TGK-14 is a manufacturer and supplier of electric and thermal energy in the Republic of Buryatia and the Trans-Baikal Territory. The installed electric capacity of the production assets is 650 MW, the thermal capacity is 2,866 Gcal/h, and the length of the heating networks reaches 941 km. The main shareholder of the company is JSC DUK. In December 2023, the functions of the sole executive body of TGC-14 were transferred to JSC DUK.