The Board of Directors of RusHydro approved the business plan and investment program of PJSC RusHydro for 2026-2030, the consolidated business plan and consolidated investment program of the RusHydro Group for 2026-2030. This is stated in the company's message.
The group's investment program for the period 2026-2030 includes the commissioning of more than 3.1 GW of new electric capacity and more than 2.5 thousand Gcal/h of new thermal capacity, as well as the construction and reconstruction of more than 5,000 km of electrical and 89 km of heating networks. In 2030, the installed capacity of the RusHydro Group's generation facilities will exceed 44.8 GW.
In accordance with the Comprehensive Plan for the Modernization and Expansion of the Main Infrastructure approved by the decree of the Government of the Russian Federation, the investment program provides for the completion of the construction of the Shkotovskaya CHPP (Artemovskaya CHPP-2), Yuzhnaya CHPP (Khabarovsk CHPP-4), Tuymaada CHPP (the second stage of Yakutskaya GRES-2) and new units at Neryungrinskaya and Partizanskaya GRES, the completion of reconstruction of Vladivostok TPP-2, in the Far Eastern Federal District.
In the period from 2026 to 2030, the RusHydro Group plans to complete the restoration of the Zagorskaya HPP-2 with a capacity of 840 MW in turbine mode and 1000 MW in pumping mode, complete the design and begin preparatory work for the construction of the Nizhne-Zeiskaya HPP with an estimated capacity of 428 MW in the Far Eastern Federal District, on the territory of the North Caucasus Federal District. 47.7 MW of new capacities of small hydroelectric power plants on the terms of the renewable energy system.
The investment program of PJSC RusHydro for 2026-2030 provides for financing measures, including technical re-equipment and reconstruction of existing hydroelectric power plants, aimed at improving the safety and technical reliability of production equipment. Within five years, the HPP capacity will increase by 154 MW of additional electric capacity without the construction of new generation facilities. The program to improve the reliability of DHC thermal generation facilities will continue to be implemented.
In total, the volume of financing of the five-year investment program of the RusHydro group will amount to 950 billion rubles, of which 530 billion rubles will be allocated for the construction of new energy facilities.
PJSC Federal Hydrogenating Company RusHydro (TIN 2460066195) unites renewable energy facilities in Russia and abroad, thermal power plants and electric grid assets in the Far East, as well as energy marketing companies and research and design institutes. As of March 31, 2025, it consists of 22 branches registered in the Russian Federation.
The share capital structure of PJSC RusHydro as of March 31, 2025: RF (62.2%), VTB (12.37%), EN+Group (9.644%), others (15.79%).
AKM Rating Agency: RusHydro is among the leaders of the fifth rating of responsibility to society and the fifth rating of the carbon footprint of the largest Russian companies.
The net profit of the RusHydro group under IFRS for 2025 amounted to 117.84 billion rubles against the negative result of 2024 — 61.16 billion rubles. Revenue increased by 14.5% to 663.77 billion rubles from 579.8 billion rubles. Revenue, including government subsidies, increased by 15.3% to 741.3 billion rubles. EBITDA increased by 45.7% to RUB 219.7 billion.