A project has been implemented at MGOK to transfer the crushing and screening plant to a closed water supply cycle

73
1
AK&M 25 April 2024 16:04

Metalloinvest has implemented a project at the Mikhailovsky GOK named after A.V. Varichev to transfer the crushing and screening factory to a closed water supply cycle. This is stated in the company's message.

Thanks to this project, the volume of industrial water returned to natural facilities at MGOK has been reduced by 70%, and by 2026 it is planned to completely eliminate water discharge.

The recycling water supply system of the crushing and screening plant is a complex complex that includes power supply facilities and pumping stations. The main pumping station with a capacity of 800 cubic meters. m per hour ensures the operation of the system by pumping water from the sump pond to the factory and back after cleaning in two stages.

Metalloinvest is a mining and metallurgical company. The company is a manufacturer and supplier of commercial hot-briquetted iron.